Keeping a legislative reporting deadline during a legacy migration

A reporting mandate landed mid-migration. The agency needed engineering capacity that could work in the legacy system and the replacement at the same time.

Engagement
ITSAC staff augmentation, 9 months
Time to first candidate slate
3 business days
Deadline outcome
Met, no extension
Contract-to-hire conversions
2

The constraint

  • The reporting deadline was statutory and could not move, while the platform underneath the reports was being replaced.
  • Internal staff were fully committed to the migration itself, leaving no capacity for the reporting work.
  • A full procurement cycle would have consumed most of the remaining schedule.

What we did

  • Solicited through a request for resume on the DIR ITSAC contract, which removed rate negotiation from the critical path.
  • Staffed a small team spanning the legacy data model and the target platform so the same people could bridge both.
  • Sequenced the reporting build to land ahead of the migration cutover, then re-pointed it after.

How it ended

  • The statutory report was filed on the original date.
  • Reporting logic was written once against agreed definitions rather than rebuilt after cutover.
  • Two contract engineers converted to agency roles after the engagement closed.

Client name withheld. This is a composite of engagement shapes we work on regularly, written so the constraints and sequencing are useful rather than as an attributed reference.